“I said ¾ of an inch. Look – it’s right there in the contract”

D’Urzo Demolition Inc. v. Damaris Developments Inc., 2012 ONSC 1912 (CanLII), released by the Ontario Superior Court of Justice on March 26, 2012, serves as a good reminder to owners and contractors of the importance of ensuring a mutual understanding of the specifications and other requirements of the work and then properly incorporating those documents and requirements into the construction contract.  For litigation lawyers, it also serves as a good reminder of the importance of ensuring that adequate and flexible evidence of damages (whether Plaintiff’s damages or a Defendant’s claim for set-off) is obtained and brought to trial.

Basic Facts

In a nutshell, D’Urzo Demolition Inc. (“D’Urzo”) was the successful bidder to demolish structures on a property in Toronto and then mechanically reduce the rubble into smaller crush.  The owner, Damaris Developments Inc. (“Damaris”), took the position that the contract required D’Urzo to crush the concrete to ¾ inch and to also demolish curbs and asphalt and remove same from the site. D’Urzo took the position that it only had to reduce the rubble to size of 3 inches (and that a smaller crush would constitute an extra) and that demolishing the asphalt and curbs and removing same from the site was not included in the scope of work and, again, constituted an extra.  At the end of the day, D’Urzo was substantially successful at trial – Damaris succeeded only in achieving a finding that the asphalt and curbs had to be demolished – D’Urzo succeeded in convincing the Court that the contract only required a 3 inch crush, that the asphalt should not have been required to be removed from the site and disposed of, and that Damaris was in breach of the contract for failing to pay.

Take Away Notes

Of note for contractors and owners – the work was put out for tender, there were competitive bids, and the parties used a standard form (CCDC2) contract and they still ended up in protracted litigation (the lien was filed in May, 2007 and trial did not conclude until December, 2011 – almost 5 years!) arising from a failure to clearly and properly set out what work was required by the contract.  If you are going to go to the trouble of putting a job out for tender and then use a detailed and established form of contract, spend the time and money to make sure that the specifications and drawings that establish the scope of work are both clear and properly incorporated by the contract.

Of note for lawyers – Damaris claimed $50,400.00 as its back charge to remove and dispose of the asphalt and curbs and provided evidence that this was what it cost.  But Master Albert found at trial that D’Urzo only had to remove the asphalt, not dispose of it.  Because Damaris’ evidence didn’t breakdown the back charge between removal and disposal, Master Albert had only D’Urzo’s evidence that the cost to remove the asphalt was $2,643.75 and he awarded that amount. This outcome highlights the risk of evidence limited to global amounts that aren’t broken down into component parts in case of divided findings at trial.

» More options